Workmen with the Sam Gaines Construction Co. of New Bloomfield are building a 120-foot bridge two miles east of New Bloomfield along County Road 436. The firm has a $315,129 contract with the Callaway County Road and Bridge Department to build the bridge over Hillers Creek.
Workmen with the Sam Gaines Construction Co. of New Bloomfield are building a 120-foot bridge two miles east of New Bloomfield along County Road 436. The firm has a $315,129 contract with the Callaway County Road and Bridge Department to build the bridge over Hillers Creek.

Two new replacement bridges are under construction this summer by the Callaway County Road and Bridge Department.

One new bridge is six miles east of Auxvasse on County Road 1011 and the other is two miles east of New Bloomfield on County Road 436.

Paul Winkelmann, county highway administrator, said Callaway County Road and Bridge Department crews expect to complete work next week on a new 70-foot bridge over Bachelor Creek along County Road 1011 about six miles east of Auxvasse.

"We started work on it in the middle of June and we have made good progress," Winkelmann said. The single-span bridge replaced a narrow-truss bridge that had a 12-ton load limit. It was a deficient bridge and is being replaced with a bridge that meets federal standards.

To help the tornado-stricken people of Dumas and surroundings, donations can be made to the Delta Area Disaster Relief Fund, care of the Delta Area Community Foundation, P.O. Box 894, Dumas, AR, 71639, or through the Arkansas Community Foundation, 700 S. Rock St., Little Rock, AR, 72202.

photo

Shirley Robinette, Eddie Getty and Sheila Davis